Welcome to your Project Integration Management

Configuration management is a process for applying technical and administrative direction and surveillance of the project implementation. Which activity is not included in configuration management?

You are a project manager for your organization. Management has asked you to help them determine which projects should be selected for implementation. In a project selection model, which of the following is the most important factor?

Of the following, which one is an input to project plan development?

Baseline variances, a documented plan to management variances, and proven methodology to offer corrective actions to the project plan are all part of which process?

Which one of the following represents the vast majority of project’s budget?

The project plan provides a baseline for several things. Which one of the following does the project plan not provide a baseline for?

Which one of the following is not beneficial to the project manager during the project plan development process?

On any project, the Lessons Learned document is created by which one of the following?

One of the requirements of project management in your organization is to describe your project management approach and methodology in the project plan. You can best accomplish this requirement through which one of the following actions?

During project integration activities, a project sponsor’s role can best be described as doing which one of the following:

Which of the following can best help a project manager during project execution?

The primary purpose of your project plan is:

Which set of the following tools is part of the project plan execution?

Which one of the following is a formal document to manage and control project execution?

EVM is used during the _______________________________.

You are the project manager for your organization. Management would like you to use a tool that can help you plan, schedule, monitor, and report your findings on your project. This tool is which one the following?

You are the project manager for your organization. When it comes to Integrated Change Control, you must ensure which one of the following is present?

You have just informed your project team that each member will contribute to the Lessons Learned documentation. Your team does not understand this approach and wants to know what the documentation will be used for. Which one of the following best describes the purpose of the Lessons Learned documentation?

You are the project manager for a pharmaceutical company. You are currently working on a project for a new drug your company is creating. A recent change in a law governing drug testing will impact your project and change your project scope. The first thing you should do a s project manager is:

The project plan provides what in regard to project changes?

You are the project manager for the HALO Project. You and your project team are preparing the final project plan. Of the following, which one is a project plan development constraint you and your team must consider?

Your project is moving ahead of schedule. Management elects to incorporate additional quality testing into the project to improve the quality and acceptability of the project deliverable. This is an example of which one of the following?

You are the project manager for the DGF Project. This project is to design and implement a new application that will connect to a database server. Management of your company has requested that you create a method to document technical direction on the project and to document any changes or enhancements to the technical attributes of the project deliverable. Which one of the following would satisfy management’s request?

All of the following are true about change requests except:

What is the difference between a project baseline and a project plan?