For each role on the following chart, enter the letter of the project you would select based on the information provided
| Project A | Project B | Which Project Would You Pick? |
Net present value | $95,000 | $75,000 | |
IRR | 13 Percent | 17 percent | |
Payback. | 16 months | 21 months | |
Benefit-cost ratio | 2.79 | 1.3 | |
4 out of 6
Make a list of the specific actions required to create a project management plan that is bought into, approved, realistic, informal.
5 out of 6
When in the project management process would you identify the need to recommend corrective actions?