Purpose:

Determines the cost baseline against which project performance can be monitored and controlled.

Objective:

Aggregate the estimated costs of individual activities or work packages to establish an authorized cost baseline.

Description:

A project budget includes all the funds authorized to execute the project. The cost baseline is the approved version of the time-phased project budget but excludes management reserves.

RASIC:

Inputs:

  • Cost Management Plan
  • Scope Baseline
  • Activity Cost Estimates
  • Basis of Estimates
  • Project Schedule
  • Resource Calendars
  • Risk Register
  • Agreements

Outputs:

  • Cost Baseline
  • Project Funding Requirements
  • Updated Project Documents

Controls:

  • Cost Aggregation
  • Reserve Analysis
  • Expert Judgement
  • Historical Relationships
  • Funding Limit Reconciliation

Task Instructions:

<?>

    1. Using the <?>, [the ?] with support from <?> is responsible for …