Purpose:
<?>
Objective:
Adherence to the performed process and associated work products to
applicable process descriptions, standards, and procedures are objectively
evaluated.
Description:
<?>
Inputs:
Outputs:
- Past Supplier Relationship Reports
-
Controls:
- QA Template
- Risk Assessment Checklist Template
- Review Log
- QA Report Template
Task Instructions:
Objectively Evaluate Processes
- Using the <?>, [the Project Manager] is responsible for notifying the Quality Manager of the project.
- Using the <?>, [the Project Manager], with support from [Quality Manager], is responsible for ensuring that a QA Analyst is assigned to the project.
- Using the QA Plan Template, [the Project Manager], with support from the QA Analyst, is responsible for identifying the QA activities for the project after completing the activity of tailoring the ORT-Project Life Cycle for the project.
- When Required: Using the QA Plan, [the Project Manager], with support from the QA Analyst, is responsible for identifying the QA activities for monitoring the Supplier’s processes in the QA Plan
- Using the Risk Assessment Checklist and past Supplier Relationship Reports [the Project Manager] is responsible for deciding and identifying the need to monitor the Supplier’s processes.
- Using the QA Plan and Review Log Template, [the Project Manager], with support from the [QA Analyst], is responsible for reviewing the Project Plan and logging the review feedback in the Review Log.
- Using the QA Plan, [the Project Manager], with support from the [QA Analyst], is responsible for ensuring the QA Plan is part of the Project Plan review and provides commitments to support the project’s QA activities.
Objectively Evaluate Work Products
- Using the QA Checklist and QA Report Template, [the QA Analyst], with [the support of the Project Manager], is responsible for conducting reviews and creating a QA Report.
- Using the QA Report, [the QA Analyst], with support from [the Project Manager], is responsible for ensuring that the QA Report is updated with the status of corrective actions.
- Using the QA Report, [the QA Analyst] is responsible for ensuring that the Non-conformances and findings from previous process reviews are addressed effectively.
- Using the QA Report, [the QA Analyst], with support firm [the Project Manager], is responsible for resolving the Non-conformances.
- When Required: